Carson City supervisors will weigh nearly $2.3 million in community center repairs Thursday

The Daily Carson City teamFrom today’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you use the Carson City Community Center or its Aquatic Facility, Thursday's meeting matters to you. The Board of Supervisors will consider nearly $2.3 million in contracts and contingency funding for repairs, led by a $1.8 million roofing contract with D&D Roofing and Sheet Metal Inc., the lowest of three bids.

The roof contract is the biggest dollar item on Thursday's agenda

Sources: Carson Now, Nevada Appeal

View as table
Value
Community Center roof$1.8M
Rapid DNA grant$450K
Aquatic attic repairs$269K
Anthony Law extension$240K
Ricciardi legal fees, up to$100K

A $269,000 contract with Simerson Construction would repair moisture damage in the aquatic facility attic. Supervisors also will consider appointing Thomas Miller acting chief of the Department of Alternative Sentencing, effective Nov. 5.

  • Rapid DNA grant: $450,000 federal, no city match
  • : two-year extension requested
  • Meeting: 8:30 a.m. Thursday, 851 E. William St.
  • Public comment: email publiccomment@carsoncity.gov by 3 p.m. today
  • Watch: carsoncity.gov/granicus or cable channel 191

Repair contracts could cost more than their base prices

$1.98 million
most the roofing contract could cost, with contingency
$295,900
most the attic repair could cost, with contingency
270
single-family lots in the Plateau subdivision

Near the end, City Manager Glen Martel will update the board, including on a new city hall project. The city recently announced a possible agreement with the Hop and Mae Adams Foundation could not come to fruition, largely because of higher interest rates.